What we did:

The project had been for the construction of a new 0.4 ml capacity single compartment reinforced concrete service reservoir, complete with flow chamber and associated pipework. The new reservoir had to operate in parallel with the existing reservoir.

Surrounding infrastructure was included to accommodate the new reservoir.

Finally, the installation of a new telemetry, SCADA and communication system was installed.