What we did:
Lay 50mm MDPE pipe work below ground from the humus distribution chamber to the periphery of both the humus and PST settlement vessels.
Installed valves to above ground pipe work and spray bars to each vessel.
Installed two rota flush pumps to existing distribution chamber.
Reinstated pathways.
Core drilled from the main distribution chamber to the new pump chamber.
Installed a new supply cable from the spare fuse switch of the LV panel (in existing ductwork) to a new MCC in the vicinity of the pumps.
Cable and connected the two pumps, 1 low level float and 4 control valves.