Aston Le Walls Sewage Treatment Works

Aston Le Walls Sewage
Treatment Works

Sector : Mechanical & Electrical Engineering

Client : Thames Water

Value : £152,000.00

The project at Aston Le walls was to remove the original media and replace it with a new filter distribution mechanism. The site was to remain operational whilst work was being carried out.

This was acheived as follows:

  • Install temporary SAFF filter, complete with pumping station and blower cubicle
  • Divert the flows through the SAFF filter until seeded
  • Isolate the flows to the filter bed and re-direct the flow from the SAFF filter to the humus tank.
  • Remove the existing media from the filter including rotating distributor and dispose off site.
  • Install new filter media.
  • Install new filter rotation mechanism and the protection flooring.
  • Enter into a phased recommissioning by diverting the settled sewage directly in the filter utilising temporary pumping station to divert the flows back through the SAFF unit prior to the humus tank.
  • Carried out daily tests to analyse the performance of the filter.
  • The test results were audited and approved by the client, the temporary SAFF filter and pumping regime were removed and the site put in full working order

Read MoreDownload Case Study

Return to Case Studies

© Damar Group 2009. All Rights Reserved

Damar Group Limited

Pows Orchard
Midsomer Norton, Radstock
Bath & N.E Somerset
BA3 2HY

Email : info@damargroup.co.uk
Tel: 01761 408 060
Fax: 01761 411 771

Contact Us