|






|
| |
Civil Engineering
Within our Civil Engineering Division we have a wealth of experience
through our fully trained workforce. All our Site Managers have
attended the CITB Site Management Safety Training Scheme (for
Building and Civil Engineering Industries), ensuring that Health
& Safety is at the forefront of our business.
We are partners with Wessex Water, Environment Agency, Bristol
City Council, Somerset County Council and Bath & N. E. Somerset
Council.
Our experience in partnering enables us to work closely with
our customers fulfilling their individual requirements. We have
successfully completed projects in bridge strengthening, sewage
treatment works, pumping stations, highways and sea defence
works.
Shaftesbury Scheme
At Wessex Water’s Shaftesbury STW site, Damar
Group were appointed Principal Contractor under CDM Regulations
for a £400k project to provide additional Sludge Storage
facilities together with various associated works. All elements
of the project were undertaken by companies under the Damar
Group umbrella.
The contract required construction of 2 no. new glass coated
steel holding tanks with a ‘domed’ GRP segmental
roof, each tank being 9.3metres diameter and 9.5 metres high
constructed off of a conical R.C. base. Damar’s ‘Civils
Division’ undertook all civil works elements of the project,
with the ‘Engineering Division’ being entrusted
with erection of the Tanks, a complex pipework manifold to facilitate
de-watering, and a common GMS staircase and access platform
constructed between the tanks to provide access to roof level
for maintenance and inspection.
Other elements of the work included a modified Sludge Collection
and Pumped Sludge Transfer system with associated underground
process pipework.
The ‘Engineering Division’ also undertook all Electrical
and Control elements of the project.
   
Longbridge Sewage Treatment Works
October 2002 saw the start of a fast-track project at Longbridge
STW near Ilminster, Somerset, for M.J.Gleeson/ECL. The works
involved major upgrading of the existing infrastructure using
the MBR, membrane technology process and upon completion, the
majority of the existing works became redundant.
Damar Group’s Civil Engineering Division were contracted
to carried out all civil work elements which included site preparation/demolition
of existing structures, 3no. new/refurbished pump stations,
R.C. slabs for various mechanical plant items, buried services
including gravity sewerage, pumped process pipework, washwater
distribution and cable-ways. Core to the whole scheme was a
partly buried R.C. tank approximately 16m x 12m x 4m deep with
integral external pipework access galleries. Internally, the
main tank was divided into 7no. compartments containing the
4no membrane units, with separate flow splitting, sludge reception
and permeate collection chambers.
‘External Works’ included new R.C. access roads
and footways with associated soft landscaping.
Under a separate sub-contract let by the main contractor, design
and installation of all above ground/surface mounted pipework
was carried out by our steel fabrication division. This included
complex ABS and welded stainless steel ‘manifold arrangements’
for the air blowers, permeate draw-off and sludge draw-off,
all associated valves included actuators, and purpose made support
bracketry.
New inlet and screening facilities required provision of several
‘small’ custom built stainless steel ‘tanks’
for flow reception and grit separation.
Damar Group’s Engineering Division carried out all mechanical
works associated with the pump stations under confined space
working conditions including temporary overpumping of incoming
flows. All ‘critical path’ elements of the works
were completed on programme in April 2003 allowing ‘plant
start-up and commissioning.
Project Pictures Longbridge
Sewage Treatment Works
   
|
|
|